Fees, timelines and documents
Your drawings may be reviewed by more than one authority. Here is how drawing approval works across DM, DDA, Trakhees and Civil Defence, and how to prepare.
In Dubai, the authority that reviews your drawings depends on where the plot is. A villa in a Dubai Municipality area, an office in Dubai Internet City and a warehouse in Jebel Ali each go through a different authority, with its own portal, requirements and review culture. On top of that, Civil Defence reviews fire and life safety on almost every project, either directly or through the main authority's process.
This guide explains how drawing approval works across Dubai Municipality (DM), the Dubai Development Authority (DDA), Trakhees and Dubai Civil Defence (DCD), what each reviews and how to prepare a package that passes. For drawing packages prepared for any of these authorities, see our engineering drawings service.
| Area | Main authority |
|---|---|
| Most mainland Dubai areas | Dubai Municipality |
| Business districts such as Internet City, Media City, Knowledge Park, Studio City | Dubai Development Authority |
| Jebel Ali Free Zone, Dubai Maritime City and several Nakheel communities | Trakhees (part of PCFC) |
| Other free zones | Their own authorities (for example DMCC, Dubai Silicon Oasis, Dubai South) |
Neighbouring communities can fall under different authorities, so confirm the authority for the exact plot before preparing drawings. In master communities, the developer's review usually comes before the authority's.
Although procedures differ, all authorities review drawings for the same broad things:
DM reviews building permits, modifications, extensions, demolition and completion for its areas, through its online system. Submissions are made by DM-registered consultants. Most DM approvals take an estimated 3 to 7 working days for a complete application. See our DM approval checklist for the documents.
DDA reviews building and fit-out works in its districts. Fit-out permits are usually requested by the tenant's registered contractor with the landlord's NOC. DDA approval typically takes an estimated 7 to 15 working days. See our DDA fit-out permit guide.
Trakhees, the regulatory arm of the Ports, Customs and Free Zone Corporation, reviews building and modification works in its areas, with engineering (CED) and environment, health and safety (EHS) aspects. In Nakheel communities under Trakhees, the master developer's NOC usually comes first. Trakhees approval typically takes an estimated 8 to 20 days. See our Trakhees permit process guide.
Civil Defence reviews fire and life safety: escape routes, detection, suppression, emergency lighting and fire separation. Depending on the jurisdiction, review is direct or coordinated through the main authority. Approval typically takes an estimated 15 to 20 working days. See how Civil Defence approval works.
Our guide to architectural mistakes that delay approval lists the most common errors.
Two other reviewers often come before the authority, and their approval is usually a prerequisite:
Master developers. In communities managed by developers such as Emaar or Nakheel, the developer checks the design against its guidelines and issues an NOC. The authority usually expects it with the application. See our guides to applying for an Emaar NOC and applying to Nakheel step by step.
Landlords and building management. For fit-outs and apartment works, the landlord or building management reviews the design against its fit-out guidelines and issues an NOC.
Planning these reviews into the programme, and preparing drawings that serve both the developer or landlord and the authority, avoids redrawing between stages.
The technical content may be similar, but each authority has its own format, requirements and submission system.
Usually a consultant or contractor registered with the authority, depending on the type of application.
Most projects with fire and life safety implications involve Civil Defence, directly or through the main authority.
Inconsistent drawings, missing information and designs that don't match the plot's controls.
In master communities, the developer's review usually comes before the authority's.
Permits have validity periods set by each authority. If works don't start or finish in time, the permit may need renewal, so plan construction soon after approval.
Tell us where your project is and what you want to build. We will confirm the authority, prepare a coordinated package to its requirements and manage the review through to approval.
For sheet sizes, file formats and scales, see how each authority wants drawings set up.
Drawing approval is one stage of the wider permit process. Our overview of the Dubai building permit process shows where it fits, from the affection plan to the completion certificate.
RELATED SERVICE
Turn your project brief into a coordinated technical drawing package. We support preparation and review of the information needed to explain the existing property, proposed work and interfaces between disciplines.
Rejections and common mistakes
The architectural drawing mistakes that most often delay approval in Dubai, from inconsistent sheets and wrong areas to missing setbacks, and how to fix them.
View details
Regulations and codes
How Dubai Municipality classifies consultants and contractors, why registration matters for permits, and how to check a firm before appointing it.
View details
Regulations and codes
The role of an engineering consultant in Dubai approvals: design, coordination, submissions, comment responses and supervision, and how to define the scope.
View details
LET’S TALK ABOUT YOUR PROJECT
Tell us the location, property type and work you have in mind.