Drawing approval in Dubai: DM, DDA, Trakhees, DCD steps

Your drawings may be reviewed by more than one authority. Here is how drawing approval works across DM, DDA, Trakhees and Civil Defence, and how to prepare.

In Dubai, the authority that reviews your drawings depends on where the plot is. A villa in a Dubai Municipality area, an office in Dubai Internet City and a warehouse in Jebel Ali each go through a different authority, with its own portal, requirements and review culture. On top of that, Civil Defence reviews fire and life safety on almost every project, either directly or through the main authority's process.

This guide explains how drawing approval works across Dubai Municipality (DM), the Dubai Development Authority (DDA), Trakhees and Dubai Civil Defence (DCD), what each reviews and how to prepare a package that passes. For drawing packages prepared for any of these authorities, see our engineering drawings service.

First: which authority reviews your drawings?

AreaMain authority
Most mainland Dubai areasDubai Municipality
Business districts such as Internet City, Media City, Knowledge Park, Studio CityDubai Development Authority
Jebel Ali Free Zone, Dubai Maritime City and several Nakheel communitiesTrakhees (part of PCFC)
Other free zonesTheir own authorities (for example DMCC, Dubai Silicon Oasis, Dubai South)

Neighbouring communities can fall under different authorities, so confirm the authority for the exact plot before preparing drawings. In master communities, the developer's review usually comes before the authority's.

What every authority looks for

Although procedures differ, all authorities review drawings for the same broad things:

  • Compliance with the rules: the Dubai Building Code, the authority's own regulations, and fire and life safety requirements
  • Fit with the plot: setbacks, height, area and use, matching the affection plan or site plan
  • Consistency: plans, sections, elevations, structural and MEP drawings that agree with each other
  • Completeness: the required sheets, calculations and supporting documents
  • Correct applicant and appointments: registered consultant and, later, contractor

Dubai Municipality

DM reviews building permits, modifications, extensions, demolition and completion for its areas, through its online system. Submissions are made by DM-registered consultants. Most DM approvals take an estimated 3 to 7 working days for a complete application. See our DM approval checklist for the documents.

Dubai Development Authority

DDA reviews building and fit-out works in its districts. Fit-out permits are usually requested by the tenant's registered contractor with the landlord's NOC. DDA approval typically takes an estimated 7 to 15 working days. See our DDA fit-out permit guide.

Trakhees

Trakhees, the regulatory arm of the Ports, Customs and Free Zone Corporation, reviews building and modification works in its areas, with engineering (CED) and environment, health and safety (EHS) aspects. In Nakheel communities under Trakhees, the master developer's NOC usually comes first. Trakhees approval typically takes an estimated 8 to 20 days. See our Trakhees permit process guide.

Dubai Civil Defence

Civil Defence reviews fire and life safety: escape routes, detection, suppression, emergency lighting and fire separation. Depending on the jurisdiction, review is direct or coordinated through the main authority. Approval typically takes an estimated 15 to 20 working days. See how Civil Defence approval works.

Steps common to every drawing approval in 2027

  1. Confirm the authority and any developer review.
  2. Gather plot and owner documents, including the current affection or site plan.
  3. Coordinate the design across architecture, structure, MEP and fire.
  4. Prepare the package to the authority's format and requirements.
  5. Obtain prerequisite NOCs, such as the developer or landlord NOC.
  6. Submit through the authority's system.
  7. Respond to comments by checking the whole set, not only the comment.
  8. Receive the approval, then carry the approved set through construction to completion.

Preparing a package that passes

  • Use the current template and notes for the specific authority
  • Check every sheet against the plot information
  • Cross-check plans, sections and elevations before submission
  • Coordinate fire drawings with the architectural layout
  • Include calculations and specifications where required
  • Keep a revision record so changes are traceable

Our guide to architectural mistakes that delay approval lists the most common errors.

Developer and landlord reviews before the authority

Two other reviewers often come before the authority, and their approval is usually a prerequisite:

Master developers. In communities managed by developers such as Emaar or Nakheel, the developer checks the design against its guidelines and issues an NOC. The authority usually expects it with the application. See our guides to applying for an Emaar NOC and applying to Nakheel step by step.

Landlords and building management. For fit-outs and apartment works, the landlord or building management reviews the design against its fit-out guidelines and issues an NOC.

Planning these reviews into the programme, and preparing drawings that serve both the developer or landlord and the authority, avoids redrawing between stages.

Frequently asked questions

The technical content may be similar, but each authority has its own format, requirements and submission system.

Usually a consultant or contractor registered with the authority, depending on the type of application.

Most projects with fire and life safety implications involve Civil Defence, directly or through the main authority.

Inconsistent drawings, missing information and designs that don't match the plot's controls.

In master communities, the developer's review usually comes before the authority's.

Permits have validity periods set by each authority. If works don't start or finish in time, the permit may need renewal, so plan construction soon after approval.

Get help with drawing approval

Tell us where your project is and what you want to build. We will confirm the authority, prepare a coordinated package to its requirements and manage the review through to approval.

For sheet sizes, file formats and scales, see how each authority wants drawings set up.

Drawing approval is one stage of the wider permit process. Our overview of the Dubai building permit process shows where it fits, from the affection plan to the completion certificate.

RELATED SERVICE

Engineering drawings

Turn your project brief into a coordinated technical drawing package. We support preparation and review of the information needed to explain the existing property, proposed work and interfaces between disciplines.

LET’S TALK ABOUT YOUR PROJECT

A clear next step starts
with the right brief.

Tell us the location, property type and work you have in mind.

This form sends your enquiry to Dubai Authority Approvals by email. It does not submit an application to an authority. Please avoid identity documents in the initial enquiry; drawings can be shared once we reply.