Trakhees and PCFC approvals

Trakhees approval in Dubai

Trakhees approval is the permit you need from PCFC's planning and development department before you build, extend, modify or fit out property on land it regulates. That covers most Nakheel communities, such as Palm Jumeirah, Jumeirah Park and Jumeirah Islands, as well as Jebel Ali Free Zone (JAFZA) and Dubai Maritime City. In most cases the developer's NOC comes first. Then Trakhees reviews the drawings, issues the permit, inspects the work and issues the completion certificate.

We prepare the architectural, structural and MEP drawings, line up the Nakheel, JAFZA or landlord NOC, and follow the application through to the permit and the completion certificate. Trakhees makes the decision. Our job is to make sure what it reviews is complete, consistent and matches the site, so it doesn't come back with avoidable comments.

What Trakhees approves and where it applies

Trakhees is the Department of Planning and Development of the Ports, Customs and Free Zone Corporation (PCFC), and it has regulated building work in its areas since 2009. Its remit covers land owned by PCFC, Dubai World and their subsidiaries, including Nakheel, Limitless and Dubai Maritime City. In practice, that usually means:

The community name is a good first clue, but the plot decides. Before any drawing is prepared, we check the affection plan or title deed to confirm Trakhees is the right authority. Most mainland plots go to Dubai Municipality instead, and DDA zones such as Dubai Internet City go to the Dubai Development Authority.

Do you need Trakhees approval for your work?

Any work that changes the layout, structure, building services or use of a property in a Trakhees area usually needs a permit. Purely cosmetic work usually doesn't, although the developer or building management may still have its own rules.

Planned workWhat it usually needs
Painting, new flooring, like-for-like replacementsUsually no Trakhees permit; check developer or building rules
New partitions, ceilings, lighting or air-conditioning changes in a unitLandlord NOC and a Trakhees modification permit
Villa extension, structural change, new pool or pergolaNakheel NOC first, then a Trakhees permit
Warehouse mezzanine, high racking, new machineryJAFZA or landlord NOC, Trakhees modification permit, fire approval
New building on a plotBuilding permit through Dubai's single building permit platform
New or changed business activity in a facilityEHS review, and an Operation Fitness Certificate where it applies

Work started without a permit can be regularised, but it usually costs more. You need as-built drawings, a structural check and sometimes changes on site. If that's your situation, tell us early; it's a common starting point.

CED and EHS approvals explained

You will still see the old department names on forms and in conversations with contractors.

CED: building and modification permits

The Civil Engineering Department is now Building Regulations and Permits. It handles the engineering side: building permits, modification permits, construction inspections and completion certificates.

EHS: how the facility operates

Environment, Health and Safety is now Environment, Health, Safety and Sustainability (EHSS). It looks at the activity, storage, machinery, chemicals and workplace safety. Its main certificate is the Operation Fitness Certificate (OFC).

A small office fit-out may only need the engineering approval. A warehouse or industrial unit often needs both: a modification permit for the physical change and an EHS review for the operation. EHS approval doesn't replace Civil Defence approval for fire and life safety, which is a separate review.

Approvals by project type

Villa renovation and extension in Nakheel communities

Nakheel reviews the design against its community rules and issues a Nakheel modification NOC. The Trakhees permit follows, based on drawings that match what Nakheel approved. If the design changes after the NOC, check whether Nakheel needs to see it again. See our villa renovation and extension approvals.

Office, retail and restaurant fit-outs

Start with the landlord's fit-out rules and NOC. The Trakhees modification permit covers partitions, ceilings and MEP changes, and the fire alarm and sprinkler layout must suit the new partitions. Restaurants add kitchen extraction, grease traps and gas, if used. More on office fit-out approval and restaurant and café approvals.

Warehouse mezzanines and racking in JAFZA

JAFZA issues a modification NOC for the change, and Trakhees permits and inspects it. Mezzanines and high racking need structural calculations and fire protection that suits the storage. Existing as-built drawings often don't match the building, so a survey usually comes first. See JAFZA approval support and warehouse mezzanine and racking approvals.

New buildings and major works

New buildings go through Dubai's single building permit platform, where Trakhees is one of the licensing authorities, and the design must follow the Dubai Building Code. For a new home, see our new villa building permit service.

Developer NOCs and Trakhees NOCs

Two kinds of NOC come up, and they're easy to confuse:

  • Developer and landlord NOCs confirm the work meets the community or building rules: the Nakheel modification NOC, the JAFZA modification NOC, or a landlord or building management NOC. These normally come before the permit.
  • Trakhees NOCs cover particular activities, such as the Minor Works NOC, the Mobilization and Signboard NOC for starting work on site, and the Demolition and Removal NOC.

We list every NOC your project needs, who applies for each and in what order, before the drawings are finalised.

Drawings and documents you'll need

The package depends on the work, but a typical modification application includes:

Most comments come from drawings that don't agree with each other, or with the site. We prepare the full set as one package, so the architecture, structure and services describe the same project. Read more about our engineering drawings for approval and MEP design.

Trakhees approval process, step by step

01

Confirm the authority and the scope

Check the plot, existing approvals and planned work, and list the permits and NOCs needed.

02

Get the developer or landlord NOC

Nakheel, JAFZA or the landlord reviews the design against its rules.

03

Prepare the drawings and documents

One coordinated set, checked against the site and the Dubai Building Code.

04

Submit to Trakhees

The application is filed online by an eligible consultant or contractor.

05

Answer comments

Each comment is answered with revised drawings, in one response where possible.

06

Permit, works and completion

Work follows the approved drawings; Trakhees inspects and issues the completion certificate.

For the portal and each step in more detail, see our guide to the Trakhees portal, steps and fees.

Inspections and completion certificates

A permit lets the work start. The completion certificate confirms it was built as approved. The certificate depends on the work:

  • Modification Completion Certificate (MCC) for changes to an existing unit or facility, such as a shop or office fit-out
  • Building Completion Certificate, partial or final, for new buildings, linked to the DEWA NOC for utility connections
  • Operation Fitness Certificate (OFC) from EHS where the business activity needs it

On Trakhees forms, "COC" usually means Certificate of Conformity, not a general completion certificate. Changes made on site must be approved before completion, and the final as-built drawings must match what was built. See also our building completion certificates service.

Why applications get delayed

  • The authority was assumed from the community name, and the plot belongs elsewhere
  • The developer or landlord NOC is missing, expired or covers a different design
  • Architectural, structural and MEP drawings don't match each other or the site
  • A mezzanine or racking was installed before the permit was applied for
  • Comments are answered one at a time instead of in one complete response

For a full list of causes and fixes, read why Trakhees applications are returned.

Trakhees approval time and cost

Time: Trakhees approval typically takes an estimated 8 to 20 days once a complete application is submitted, depending on the permit type and the scope of work. Preparing drawings, getting the developer NOC and answering comments come on top of that, and inspection and completion follow after the works.

Cost: Trakhees authority fees for most approvals are an estimated AED 1,500 to 4,000, depending on the permit and the area of work; modification works on an existing property are an estimated AED 1,000. Developer fees, Civil Defence, DEWA and any Operation Fitness Certificate are separate, as is our fee for drawings, submission and follow-up. We quote authority fees and our own fee separately, in writing, before work starts.

Trakhees, Dubai Municipality or DDA: which applies?

AuthorityTypical areas
Trakhees (PCFC)Nakheel communities, JAFZA, Dubai Maritime City and other PCFC and Dubai World land
Dubai MunicipalityMost mainland plots, including many Emaar villa communities, with the developer NOC first
Dubai Development AuthorityDDA zones such as Dubai Internet City, Dubai Media City and Dubai Science Park

See Dubai Municipality approval and DDA approvals. If you're not sure, send us the plot details and we'll confirm.

How we help

You get a written scope before work starts, listing the approvals, drawings, responsibilities and exclusions.

Trakhees approval FAQs

It's the permit from Trakhees, PCFC's planning and development department, for building, modification and fit-out work in its areas, followed by inspection and a completion certificate.

Land owned by PCFC, Dubai World and their subsidiaries, including most Nakheel communities, JAFZA and Dubai Maritime City. We confirm it for your plot from the affection plan or title deed.

For work in a Nakheel community, usually yes. Nakheel approves the design against its community rules, and the Trakhees permit follows on matching drawings.

CED, now Building Regulations and Permits, approves the building work. EHS, now EHSS, reviews how the facility operates and issues the Operation Fitness Certificate.

Not if the work adds a mezzanine, racking, partitions or changes to services. JAFZA's modification NOC and a Trakhees permit are normally both needed.

An estimated 8 to 20 days once a complete application is submitted. Drawings, NOCs and comment rounds add to the overall timeline.

Authority fees for most approvals are an estimated AED 1,500 to 4,000, and modification works an estimated AED 1,000. Developer fees, other approvals and our consultancy fee are quoted separately.

No. Trakhees makes its own decisions. We prepare a complete, consistent submission and answer comments quickly, which avoids most unnecessary delays.

Tell us what you are planning

Check your Trakhees approval route

Send the community or zone, plot or unit number, what you plan to change and any drawings or approvals you have. We'll tell you which approvals apply, in what order, and what we need to start. The form sends your enquiry to us by email; you can share drawings once we reply. Please don't include identity documents in the first enquiry.

This form sends your enquiry to Dubai Authority Approvals by email. It does not submit an application to an authority. Please avoid identity documents in the initial enquiry; drawings can be shared once we reply.