For developers, industrial operators and building owners whose project touches a road, a car park or a drainage network. We prepare the access, parking, grading and drainage drawings that RTA, Dubai Municipality and the utility providers review, and coordinate the NOCs that follow.
A building permit covers what happens inside the plot line. The moment a project needs a new gate onto a public road, a car park that discharges rainwater, or a sewer connection across the verge, a second set of reviewers gets involved, and they read a different kind of drawing.
Infrastructure design is the civil engineering around and between buildings: where vehicles enter and leave, how they circulate and park, where rainwater goes, how the site connects to sewers and utility networks, and how all of this is built without damaging services already in the ground. In Dubai these questions are answered on drawings that go to the Roads and Transport Authority (RTA), Dubai Municipality's sewerage and drainage teams, and the utility providers, usually alongside the main building application.
We prepare those drawings and coordinate the NOCs that depend on them. The authorities decide whether to approve. Our role is to give them a design that is complete, follows their published manuals and guidelines, and is consistent with the architectural and MEP package.
Most of our infrastructure work sits at the scale of a single plot or a small group of plots: a warehouse yard, a showroom forecourt, a school drop-off, a residential building's basement ramp and visitor parking. The typical elements are:
Location and geometry of entrances and exits, turning paths for the largest expected vehicle, sight lines, kerb and footpath treatment where the access crosses the verge, and how the access ties into the existing road.
Circulation aisles, parking bays including accessible bays, loading and service areas, ramps, pedestrian routes and the signage and road markings that make the layout work.
Finished levels across the site, falls to gullies or channels, pipe networks, and the connection or disposal arrangement agreed with the drainage authority.
The route of the foul sewer connection to the public network, and coordination of electricity, water, telecoms and irrigation routes so they don't clash in the verge or under the access.
Building-scale plumbing, drainage stacks and the electrical installation are part of MEP design. Infrastructure design picks up where those systems leave the building and meet the site and the public network. On larger projects the two packages share levels and connection points, so we prepare or check them together.
You are likely to need an infrastructure package if any of these apply:
The earlier these drawings start, the better. Access position affects the ground-floor plan, the ramp location and sometimes the structural grid, so leaving it until after the architectural design is fixed often means redrawing both.
Several bodies review different parts of the same site, and in free zones and master communities the picture changes again. The table shows the main mainland reviewers and what they publish.
| Reviewer | What they look at | Relevant published service or guidance |
|---|---|---|
| RTA (access and right-of-way) | Entrance and exit locations and geometry, the effect on traffic, works in the road reserve | "Apply for Access Design Study", for consultants, through the RTA right-of-way permits portal |
| RTA e-NOC (infrastructure NOCs) | Utility and infrastructure works within or next to the right-of-way, collecting comments from each service provider | NOC types include Design, Construction, Trial Trench, Service Information, Shop Drawing and Design & Build |
| Dubai Municipality (sewerage and drainage) | Sewer and stormwater connections, construction near existing networks, diversion of lines | Sewerage and Stormwater Design Guidelines (January 2025 edition); NOC for construction close to sewerage and stormwater networks |
| DEWA and telecom providers | Clearance from and protection of their cables and pipes, new connections | Infrastructure NOC requests through the e-NOC system |
| Developer or free-zone authority | Community infrastructure standards, connection points, landscaping interfaces | Varies by area: Trakhees, DDA, JAFZA and master developers apply their own rules |
The RTA approvals and DEWA approvals pages explain each authority's process in more depth. For sites with many interfaces, our NOC coordination service manages the full set in parallel.
Rail corridors: sites near the Dubai Metro or Tram fall within the rail right-of-way. RTA's Rail Agency endorsed dedicated NOC submission guidelines for infrastructure works in that zone in March 2024, so these sites need an extra layer of review.
The exact set depends on the reviewer and the stage, but an infrastructure submission for a typical plot draws from this list:
We review the affection plan, community infrastructure information and existing services records, and arrange a topographic and utilities survey if one isn't available.
Our team · surveyor
Entrance positions and vehicle types are tested against the road layout. Where an RTA access design study is needed, the layout is prepared and submitted early, with the building or demolition permit details it asks for.
Consultant · RTA
The site layout, finished levels and drainage network are designed together with the architectural ground floor and MEP drainage, so gate levels, ramps and outfalls agree.
Consultant
Design-stage NOCs are requested from the service providers, and the drainage and sewer connection proposals are submitted to Dubai Municipality. Comments are answered with revised drawings.
Registered consultant
Once the contractor is appointed, construction-stage NOCs and any right-of-way work permits are obtained before excavation in the road reserve.
Contractor · consultant
As-built drawings of the infrastructure are prepared for handover and completion. Our as-built drawings service covers this stage.
Contractor · consultant
Infrastructure NOCs run alongside the building permit rather than after it. Our guide to drawing approval across DM, DDA, Trakhees and DCD shows how the streams fit together.
Some authority figures are published. RTA lists its access design study as free of charge with a delivery time of 10 working days, which it notes may vary by project. Infrastructure NOCs issued through e-NOC are listed as valid for six months from issue of the final NOC. Dubai Municipality describes its NOC for construction close to sewerage and stormwater networks as a 7-day service. These figures count from a complete submission, and they don't include design time or comment rounds.
Our design fee and the overall timeline depend on:
Usually, yes, where the access connects to a public road. RTA offers an access design study service for consultants that reviews the proposed entrances and exits against its standards and returns approved drawings. It asks for a building or demolition permit from the permit authority as part of the application, so it runs alongside the main permit.
A design NOC is requested at design stage, when the consultant is involved, so the service providers can comment on the proposal. A construction NOC is requested once the contractor is appointed and is needed before works in or near the right-of-way begin.
It depends on whether a stormwater network is available near the plot and what Dubai Municipality or the area authority agrees. The design follows DM's Stormwater Design Guidelines. We confirm the disposal option early, because it affects levels across the site.
Parking requirements depend on the use, the floor area and the area's planning rules, and they are checked by the permit authority. We calculate the requirement for your plot from the applicable rules at the start of design, rather than relying on a general ratio.
Rarely as a separate package. Villas normally connect to community networks set out by the developer. A new driveway or gate position, or a pool discharge, may still need developer or authority input, and we handle it as part of the villa design.
On this page
Site access or drainage question?
Send the affection plan or plot number and a sketch of where you want the gate or car park. We will tell you which reviews to expect.
Service
RTA NOCs and permits for site access, works in the road reserve, utility connections and traffic impact studies in Dubai. Documents, steps and common delays.
Read more
Service
DEWA building NOCs, load approvals and electricity and water connections for new buildings, extensions and fit-outs in Dubai: documents, steps and common delays.
Read more
Service
Get support for Dubai Municipality approval: drawings, NOCs, permits, submissions and completion coordination. Check the approval route for your project.
Read more
Service
One team to track every NOC your Dubai project needs: developer, building management, DEWA, Civil Defence, RTA, telecoms and more, sequenced around your permit.
Read more
Service
Coordinate mechanical, electrical and plumbing systems around the proposed space and equipment. We help connect the architectural layout to practical service routes, demand information and technical submissions.
Read more
Service
Approvals for warehouse mezzanines, high-bay racking, new storage uses and industrial unit changes in Dubai: Civil Defence, structural checks, Trakhees and DM.
Read more
Guide
RTA publishes separate infrastructure NOC services for design and construction within the right of way.
Read more
Guide
The useful starting point for an electrical application is an accurate description of connected equipment and the existing supply.
Read more
Guide
Different bodies review different aspects of a proposal.
Read more
Share a few details and we will tell you which approvals apply, what documents you need and how we can help. There is no obligation.