DDA fit-out permit: a tenant's step-by-step guide

Fitting out a unit in a DDA business district? Here is how the landlord's requirements and the DDA fit-out permit fit together, step by step.

The Dubai Development Authority (DDA) regulates building and fit-out works in many of Dubai's business districts, including Dubai Internet City, Dubai Media City, Dubai Knowledge Park, Dubai Studio City, Dubai Production City and Dubai Outsource City. Tenants often still call it TECOM, after the group that developed these districts. If you are fitting out an office, studio, shop or other unit there, the DDA fit-out permit is the main regulatory approval.

This guide walks through the DDA fit-out permit from a tenant's point of view: what to do before applying, how the landlord's requirements fit in, the review and works stages, and completion. For a detailed list of documents, see our companion guide on documents required for a DDA fit-out permit, and for project support, our DDA approval service.

DDA and TECOM: what the names mean

TECOM Group developed and manages many of the business district buildings. The Dubai Development Authority is the regulator that reviews and approves building and fit-out works in those districts. In practice, tenants deal with both: the building owner or manager (often TECOM or another landlord) for landlord consent, and DDA for the permit.

Before you apply

Read the landlord's fit-out guidelines

Every building has fit-out guidelines covering design standards, approved contractors, working hours, deposits and the landlord's own review. Read them first; designs that ignore them get returned by the landlord before DDA ever sees them.

Check the unit's services

Confirm the electrical load, AC capacity and any chilled water allocated to the unit, especially if you plan a server room, kitchen or heavy equipment.

Appoint the right team

The application is usually submitted by the fit-out contractor registered with DDA, supported by a designer or consultant for the drawings.

The step-by-step process

  1. Brief and design. Agree the layout, ceilings, finishes, MEP and fire requirements, following the landlord's guidelines.
  2. Landlord review and NOC. Submit the design to the landlord, address their comments and obtain the NOC.
  3. Prepare the DDA submission. Drawings, contractor appointment, tenancy documents, the landlord NOC and any other required NOCs. See the DDA document checklist.
  4. Submit through DDA's system. The contractor submits the fit-out permit application.
  5. DDA review. DDA reviews the drawings and documents and may issue comments.
  6. Respond to comments. Revise the drawings and resubmit where required.
  7. Permit issued. Works can start once the permit is issued and the landlord's site access is arranged.
  8. Carry out the works to the approved drawings, within the building's rules.
  9. Inspections and Civil Defence completion. Fire systems are inspected and the Civil Defence completion obtained.
  10. Fit-out completion certificate. DDA issues the completion once the requirements are met.

How long it takes

DDA approval typically takes an estimated 7 to 15 working days once a complete application is submitted. The landlord's review, design development, comment rounds, the works themselves and completion add to the overall programme.

Fees in 2027

In 2027, authority fees for most DDA approvals are an estimated AED 1,020 – 3,000, depending on the area and scope. The fit-out permit fee is area-based. Landlord fees, deposits and professional fees are separate.

What DDA typically checks

  • Layout and occupancy, including escape routes and exits
  • Fire and life safety: sprinklers, detection, emergency lighting
  • Accessibility where required
  • MEP design consistent with the base building's capacity
  • Consistency between drawings and documents
  • Contractor registration and tenancy details

Planning the fit-out period

Most landlords give tenants a fixed fit-out period, often with reduced or no rent, before the lease starts in full. The approval process eats into that period, so plan it from the date you get the keys:

  • Week one: confirm the landlord's guidelines, survey the unit and agree the brief.
  • Design stage: complete layout, ceilings, MEP and fire drawings, and price the works.
  • Landlord review: allow time for the landlord's comments and NOC.
  • DDA review: allow an estimated 7 to 15 working days once the complete application is in.
  • Works: the remaining time, ideally with long-lead items such as joinery and AC equipment ordered once the design is fixed.
  • Completion: Civil Defence inspection and the fit-out completion certificate before you trade.

If the fit-out period looks too short for this sequence, raise it with the landlord before signing, not after.

Moving into an existing fit-out

Some tenants take over a unit with an existing fit-out from the previous occupier. This can save time and money, but any change to partitions, ceilings or services still needs approval, and the existing fit-out must have been properly completed. Ask the landlord for the previous fit-out completion certificate and approved drawings before relying on them.

Common delays

  • Ignoring the landlord's fit-out guidelines
  • Fire drawings that don't match the architectural layout
  • Expired tenancy or contractor documents
  • MEP loads exceeding the unit's allocation
  • Layout changes during works without a revision
  • Missing Civil Defence completion at the end

Frequently asked questions

Usually the tenant's fit-out contractor, registered with DDA, with the tenant's documents and the landlord's NOC.

Yes. DDA expects the landlord's NOC with the application.

No. Works should start only after the permit is issued and site access is arranged with the landlord.

Yes. Fire and life safety is part of the fit-out, and a Civil Defence completion is usually required before DDA's fit-out completion.

No. DDA covers specific districts. Other free zones have their own authorities.

Get help with your DDA fit-out

Send us the building, unit and your plans. We will check the landlord's guidelines, prepare the drawings and coordinate the landlord NOC, DDA permit and completion. For office projects, see our office fit-out approval service, and for the fire stage, how Civil Defence approval works.

RELATED SERVICE

DDA / TECOM approval

Plan a fit-out within the relevant Dubai Development Authority jurisdiction with a coordinated drawing and document package. We help clarify landlord requirements, the permit scope and the information needed from your appointed contractor.

LET’S TALK ABOUT YOUR PROJECT

A clear next step starts
with the right brief.

Tell us the location, property type and work you have in mind.

This form sends your enquiry to Dubai Authority Approvals by email. It does not submit an application to an authority. Please avoid identity documents in the initial enquiry; drawings can be shared once we reply.