Permits & NOCs · Interior fit-out of units
For tenants, owners and fit-out contractors taking on a shell, a refurbishment or a change of layout inside a unit. We work out which approvals apply to your unit, prepare the drawings and documents, and coordinate the permit, Civil Defence approval and fit-out completion.
A fit-out looks like an interior job, but the approvals treat it as building work. New partitions change escape routes, a moved ceiling changes sprinkler coverage, and a new kitchen or server room changes electrical and cooling loads. That is why most fit-outs need more than the landlord's say-so.
The difficulty for most clients is not any single approval. It is working out which ones apply. The same 200 m² unit can need a Dubai Municipality decoration permit on Sheikh Zayed Road, a DDA fit-out permit in a TECOM business park, a Trakhees modification permit in a Jebel Ali area, or a free zone's own approval, all before the activity-specific approvals for a restaurant, clinic or salon.
This page is the general fit-out route. Once you know your unit type, our pages for office fit-out, restaurant and F&B fit-out, retail and showroom fit-out, salons, spas and gyms and clinics and pharmacies go into the specific requirements.
Authorities draw a line between interior works that stay inside the unit and don't affect the building, and works that change the building itself. Where your project sits on that line decides the permit type.
The Dubai Development Authority states this directly for its zones: structural changes, a change of use or additional floor area need a building modification request rather than a fit-out permit, and coring has limits on size and distance from columns. If your works include any of these, see our change of use and warehouse and mezzanine services as well.
The authority follows the location of the building, not the type of business.
| Where the unit is | Fit-out approval | Key points |
|---|---|---|
| Mainland Dubai | Dubai Municipality decoration works permit | Needed for commercial, office, professional and industrial units over 100 m². Units of 100 m² or less, and units inside malls and similar trade centres, are exempt from the permit but must still meet Civil Defence requirements and have the owner's written consent. |
| DDA zones (Internet City, Media City, Studio City and others) | DDA fit-out permit | Applied for by the contractor. DDA lists a fee of AED 0.90 per ft² (minimum AED 200, maximum AED 10,000) plus AED 20 in Knowledge and Innovation Dirham, 2 working days, and 6 months' validity. |
| Trakhees areas (PCFC, Jebel Ali and many Nakheel properties) | Trakhees CED modification NOC / permit | Trakhees states that a modification NOC or permit is mandatory before any modification or fit-out works, designed to the Dubai Building Code 2021. Engineers must be accredited. Works close with a Modification Completion Certificate. |
| JAFZA, DMCC, DSO, DIFC and other free zones | The free zone's own engineering or fit-out team | See JAFZA, DMCC and the free zones guide. In DMCC, for example, a company requests a fit-out NOC addressed to Concordia through the DMCC member portal. |
Whichever authority applies, Dubai Civil Defence requirements run alongside. DCD reviews engineering drawings through its smart services platform, and the DDA, for example, requires the DCD completion certificate before it issues the fit-out completion certificate.
Written consent from the owner and the building's fit-out rules: working hours, protection, hot works, deposits and the building's own drawing review. This comes first.
In master communities and mixed-use districts, the developer or its community management may issue its own NOC, especially where works affect shared systems or appearance.
The DM decoration permit, DDA fit-out permit, Trakhees modification permit or free zone approval, depending on location.
Fire and life safety drawings: escape routes, fire alarm, sprinklers, emergency lighting, signage and any special hazards.
DEWA approval if the electrical load increases or a new meter is needed. See DEWA approvals.
Food safety for F&B, health authority approval for clinics, and other sector approvals tied to the trade licence.
Dubai Municipality's decoration permit rules (Administrative Resolution No. 85 of 2019) are written for units used for commercial, professional, industrial or office purposes. For apartments, the controlling approvals are usually the building management or owners' association and, where relevant, the master developer. Under the jointly owned property law (Law No. 6 of 2019), substantial changes to a building's structure or external appearance need approval from the master developer, the Dubai Land Department and the competent authority.
In practice, an apartment kitchen or bathroom refurbishment mostly runs through the building's NOC and access process, while anything that touches structure, shafts, façade or shared services goes further. Our article on the apartment renovation NOC covers this in more detail. Villa works are covered on our villa renovation page.
Where the base build drawings are missing or the unit has been altered before, an as-built survey is usually the first task. Our engineering drawings service prepares the authority package itself.
Check the authority, the permitted use, the unit area and the building's fit-out manual before the design is fixed.
You + our team
The layout and MEP design are prepared and submitted to the landlord or building management. Their comments are closed out first.
Designer · landlord
The contractor or registered consultant submits the package to the permit authority and Civil Defence, with the landlord NOC and any developer NOC.
Contractor / consultant
Once approved, works start within the permit's validity. Hot works, deliveries and noisy works follow the building's rules.
Contractor
Fire systems are tested and inspected. Civil Defence issues its completion once the installation matches the approved drawings.
DCD · contractor
The authority closes the permit with a completion certificate. This then supports the trade licence, activity approvals and the landlord's handover.
Authority · landlord
Official service standards such as DDA's 2 working days count from a complete application. They don't include design or landlord review time. For a broader look at the process, read our guide to fit-out approval in Dubai.
Approvals are issued by the landlord, developer and authorities, not by us. Our job is to make your package complete and keep it moving.
On the mainland, Dubai Municipality exempts units of 100 m² or less, and units inside malls, from the decoration permit. Civil Defence requirements and the owner's consent still apply. Free zones and DDA zones have their own rules, so check by location.
Usually the contractor. Dubai Municipality decoration permits are filed by a DM-approved contractor, and DDA lists contractors as the applicants for its fit-out permit. The tenant provides the lease, licence, landlord NOC and appointment letter.
In most cases, yes. Civil Defence reviews the fire and life safety design and inspects the installed systems. Some authorities, such as DDA, require the Civil Defence completion before issuing the fit-out completion.
Unapproved works can block licensing, insurance and handover, and can bring fines. The usual fix is an as-built survey followed by a regularisation application, sometimes with remedial works.
Authority steps can be short once the application is complete. DDA lists 2 working days. The overall time depends mostly on design, landlord review, Civil Defence and any activity approvals.
Rules and authorities differ by area. These guides cover what applies in each community.
On this page
Taking on a new unit?
Send us the building name, unit size and intended use. We will tell you which approvals apply before you start design.
Service
Plan an office that supports your team while coordinating the permissions for partitions, services and building access. We help organise the fit-out brief and the technical information needed for submission.
Read more
Service
Coordinate the food operation, kitchen design and premises approvals before committing to a fit-out. We help bring the operator’s menu and equipment brief into the technical submission process.
Read more
Service
Prepare a retail space around its products, customers and building requirements. We help coordinate the fit-out information for display areas, storage, services and relevant approvals.
Read more
Service
DCD approval support in Dubai for fire and life-safety drawings, fire alarm and firefighting coordination, submissions, inspections and completion.
Read more
Service
DDA approval support for fit-out, renovation and construction in Dubai. Coordinate drawings, NOCs, permits, submissions and completion requirements.
Read more
Guide
A practical fit-out register lists each permission, issuer, scope, owner and status.
Read more
Guide
Self-decor is a label that should not be used as a shortcut for every interior alteration.
Read more
Guide
Apartment works can interact with common pipes, ventilation, fire systems and neighbouring units.
Read more
Guide
Inspection preparation should compare the completed work with the approved package and required evidence.
Read more
Share a few details and we will tell you which approvals apply, what documents you need and how we can help. There is no obligation.