For shops, restaurants, cafés, hotels and event organisers who need a sign on the façade or a temporary tent or structure. We work out which authority issues each permit, prepare the drawings and documents, and coordinate the safety approvals behind them.
Two permits that businesses often leave until the last week before opening: the sign over the door and the tent for Ramadan or an event. Each is issued by a different authority, each has its own rules, and each can delay an opening if it is missing.
They share a pattern. The permit itself is often quick, but it depends on things that aren't: a sign that fits the façade rules or a tent with Civil Defence approval. These are design and planning questions, best answered before the fit-out drawings are fixed.
This page sets out who issues what, the main rules set by the authorities, and where projects tend to go wrong. The authorities issue the permits. We help you prepare for them and coordinate the applications.
Planning to serve shisha? It has its own permit and premises rules: see our shisha café approval services.
Under Decree No. 6 of 2020 regulating advertisements in Dubai, no one may display an advertisement in any advertising space without a permit. The decree also requires anyone carrying on an economic activity to display a sign on their premises' façade showing the activity and trade name. A shop sign is therefore both required and regulated.
The decree assigns advertising permits to different entities depending on where the advertisement is:
| Where the sign or advert is | Competent entity under Decree No. 6 of 2020 |
|---|---|
| Façades of commercial outlets and centres | The economic department (now the Department of Economy and Tourism) |
| Vacant land, buildings, coastal, water and desert areas | Dubai Municipality |
| Roads, right of way, transport and vehicles | RTA |
| Free zones and special development zones | The zone's own authority |
The system has since been consolidated. Mada Media, established under Law No. 20 of 2024, operates under a concession with RTA and Dubai Municipality and launched a unified online platform in April 2025. It covers advertising on the right of way, public transport, commercial vehicles, private land and buildings. In May 2026, Dubai's Media Office confirmed that the Department of Economy and Tourism issues permits for trade-name signage on shopfronts.
The Outdoor Advertising Manual, issued in 2024 by RTA and Dubai Municipality in coordination with Mada Media and approved by Administrative Resolution No. 180 of 2025, sets the technical rules. For shopfront trade-name signs, the published points include:
Larger advertising structures have their own services. Dubai Municipality lists permits for billboards on buildings and on land, roof and pole advertisements, approval of billboard advertising content, and approval of signboard design in historical areas. These signs also need structural design and fixing details, and often the building owner's consent.
Under the decree, fines for violations range from AED 1,000 to AED 15,000, doubled for a repeat within a year up to AED 30,000. The competent entity can also remove unpermitted adverts at the violator's cost, plus an administrative charge.
Ramadan tents, event marquees, seasonal kiosks and outdoor canopies are temporary, but they are still structures with occupants, electrics and fire risk. The permit route depends on who is putting up the tent and where.
The Department of Economy and Tourism has a temporary tent permit for hotel events, applied for through its ePermits system. Its published requirements include a Civil Defence approval or NOC and a Dubai Municipality approval letter. Once the tent permit is issued, the hotel applies for the event permit for that venue.
Dubai Municipality lists a permit for temporary land use, covering temporary activities linked to projects under construction or to events and entertainment. It also lists a separate temporary winter camp permit for personal family use during the camping season.
DDA lists an event permit for its TECOM areas, which needs stamped structural drawings where temporary construction is involved, and a temporary construction permit. DDA publishes AED 5,000 and 4 working days for the temporary construction permit, valid for 6 months.
Trakhees publishes a modification NOC application form specifically for temporary facilities in its jurisdiction.
Mainland or free zone, shopfront or billboard, hotel or restaurant: the answer decides which authority and system to use.
Our team
Façade proportions for signs, location and access for tents.
Our team + you
Sign elevations or tent structure and layout, with landlord and developer consents.
Consultant · specialist contractor
Civil Defence and structural approvals are obtained where the main permit depends on them.
Consultant · Civil Defence
The application goes through the issuing authority's system, by you or your licensed contractor, with our coordination.
Applicant · authority
Yes. Dubai's advertising decree requires a trade-name sign on the façade and a permit for any advertisement. Shopfront trade-name sign permits are issued by the Department of Economy and Tourism, and the sign must follow the Outdoor Advertising Manual.
No. The published shopfront rules allow one trade name per establishment, displayed horizontally with Arabic above English.
Hotel operators apply to the Department of Economy and Tourism for a temporary tent permit. Its requirements include Civil Defence approval and a Dubai Municipality approval letter.
On this page
Opening soon?
Tell us the location and whether you need a sign or a tent. We will tell you which permits apply and what to check first.
Service
Shisha has its own permit, with location, premises and ventilation rules to check before you sign a lease.
Read more
Guide
A restaurant opening combines business activity, suitable premises, food-layout requirements, fit-out work and operational readiness.
Read more
Guide
A restaurant fit-out is shaped by what is prepared, stored, cooked and served.
Read more
Guide
RTA publishes separate infrastructure NOC services for design and construction within the right of way.
Read more
Service
Restaurant and café approvals in Dubai: food-safety layout assessment, hood suppression, grease traps, exhaust, LPG and Civil Defence, planned before you build.
Read more
Service
Fit-out approvals for shops and showrooms in Dubai malls and street units: landlord and authority permits, display loads, shopfronts, fire safety and handover.
Read more
Service
DCD approval support in Dubai for fire and life-safety drawings, fire alarm and firefighting coordination, submissions, inspections and completion.
Read more
Service
Plan works that interact with roads, access or the public right of way with the correct information from the start. We help coordinate the location, design brief and submission responsibilities.
Read more
Service
Get support for Dubai Municipality approval: drawings, NOCs, permits, submissions and completion coordination. Check the approval route for your project.
Read more
Share a few details and we will tell you which approvals apply, what documents you need and how we can help. There is no obligation.