Tell us what you plan to do, where the property is and what stage the project has reached. Existing drawings, management instructions and reviewer comments help establish the starting point.
We review the title deed or lease, the affection plan, any approved drawings and the developer's community rules. If the original drawings are missing, we arrange a measured survey and prepare as-built drawings so the design starts from the building as it actually is.
Identify the required design, coordination and execution services. Agree the deliverables, exclusions, appointment structure and any specialist responsibilities before proceeding.
This becomes a written scope: which authorities and developers are involved, which drawings and documents we prepare, what you or your contractor provide, and what is excluded. It also notes the authority fees, which are paid separately and are shown as estimated ranges until the authority issues its invoice.
Gather the applicant and property documents, develop the agreed technical information and coordinate interfaces. Maintain a single current drawing set and record outstanding decisions.
Architectural, structural and MEP drawings are coordinated with each other and checked against the Dubai Building Code, Al Sa'fat and the UAE Fire and Life Safety Code where they apply. Drawings are issued as PDF sets for submission and as AutoCAD DWG files for your records and your contractor.
Confirm the submission route and authorised applicant. Track comments and revisions against the actual scope; do not treat one consent as permission for unrelated works.
Developer NOCs usually come first, then the authority permit, with Civil Defence, DEWA or other NOCs requested in the order the authority needs them. When comments arrive, we revise the drawings, explain the changes and resubmit, keeping one record of what was approved at each stage.
Where included in the appointment, coordinate permitted site work, inspection preparation and completion documents. Review changes before they are built and preserve a useful handover record.
That can include carrying out the works through our execution services, preparing for Civil Defence and authority inspections, and assembling test certificates and as-built records for the completion certificate.
Once a complete submission is accepted, each authority's review usually takes the periods below. These are estimated ranges; comments, resubmissions and the time spent preparing drawings and NOCs come on top.
| Authority or developer | Typical review period |
|---|---|
| Dubai Municipality | 3 to 7 working days |
| Dubai Development Authority | 7 to 15 working days |
| Dubai Civil Defence | 15 to 20 working days |
| Trakhees | 8 to 20 days |
| JAFZA | 5 to 7 working days |
| Emaar | 3 to 5 working days |
| Nakheel | about 5 working days for standard reviews; extensive works take longer |
Our guide on how long a building permit takes explains what affects these times.
Most of these are avoided by settling the scope and checking the records at the start. See common building permit mistakes for more detail.
The FAQ answers the questions we hear most, such as which authority applies and what to send for a quote. You can also read about our team, or send the property location and a short description through the project enquiry form and we will reply with the approvals that apply and a written scope.