Putting solar panels on a roof in Dubai is not a weekend DIY job, and it is not something any electrician can connect to the grid. Every grid-connected system goes through DEWA's Shams Dubai process, and only companies DEWA has enrolled for solar work can file it.
That rule protects the network, but it also means the owner sits in the middle of several parties: DEWA, an enrolled consultant or contractor, often a master developer or landlord, and sometimes a structural engineer who has to confirm the roof can carry the load. Most delays we see come from those parties working in sequence instead of in parallel.
This page explains how the approval works for villas, residential buildings, warehouses and commercial roofs, what DEWA asks for, and where projects tend to stall. DEWA alone issues the solar NOC, design approval and connection. Our role is to prepare, coordinate and follow up.
Shams Dubai is DEWA's initiative for distributed solar generation. Owners install photovoltaic panels on their building, use the electricity on site, and export any surplus to DEWA's network. DEWA describes this as net metering: exported surplus is credited and offsets future consumption, and DEWA's FAQ states that credit rolls over indefinitely to later bills.
DEWA's guidance limits renewable generators to rooftops, façades and other existing structures, such as car-park shades. Ground-mounted arrays on open land are not part of the residential scheme.
Only consultants and contractors enrolled with DEWA as Electrical & DRRG Solar PV Consultants or Contractors can apply. DEWA publishes the list of eligible companies.
Before connection, the customer signs a connection agreement with DEWA and presents an operation and maintenance contract with an enrolled provider.
Credit stays with the account: DEWA's FAQ says a generator can be transferred to a new owner or tenant by agreement, but accumulated credit cannot. If you plan to sell or move, factor that into how you size the system.
Any system that connects to DEWA's grid needs the Shams Dubai approvals, whatever its size. The projects we are typically asked about include:
Each brings its own approval layer on top of DEWA:
Not sure who owns or controls your roof? That is the first thing we establish, because it decides whose signature goes on the application.
DEWA divides the connection into three stages: getting solar permits and connections, inspection and connection, and generation. In practice the work around those stages looks like this:
Look at usable roof area, shading from parapets, water tanks and AC units, orientation, and the building's existing electrical load and meter arrangement. Confirm who owns the roof and whose consent is needed.
Owner + our team
Where the property sits in a master community or is leased, obtain the developer's modification NOC or the landlord's NOC before DEWA submission. Developers may ask for a roof layout and elevations showing how visible the panels will be from the street.
Owner · developer · landlord
The enrolled consultant or contractor uploads the required documents and technical drawings in DEWA's system. DEWA issues the solar NOC, then the solar design approval, and raises its invoice.
Enrolled consultant / contractor · DEWA
The enrolled contractor installs mounting, panels, inverters, protection and cabling in line with the approved design. Community work-permit rules (working hours, access, debris) still apply.
Enrolled contractor
The contractor notifies DEWA that the installation is ready. DEWA inspects the site, the connection agreement is signed, the meter is installed and the system is connected to the grid.
DEWA · contractor · owner
Once live, exports appear as credit on the DEWA bill. The O&M contract covers cleaning, checks and repairs, which matter in Dubai's dust.
Owner · O&M provider
DEWA states that solar NOCs can be obtained online. The full timeline depends mostly on how quickly consents, drawings and comments are resolved, not on any single DEWA step. For the wider DEWA picture, see our DEWA approvals service and the guide to Shams Dubai fees and net metering.
The exact upload list sits in DEWA's system and is handled by the enrolled company. Expect to gather the following:
A solar array changes how a roof is used. Thinking about these points early keeps the design, the developer review and the DEWA review aligned.
Panels add dead load, and wind uplift on Dubai's exposed rooftops is significant. Penetrating fixings affect waterproofing; ballasted systems add weight. Older villas and lightweight warehouse roofs deserve a proper check rather than an assumption.
Developers care about what the street sees. Low-tilt arrays set back behind parapets are generally easier to approve than frames that rise above the roofline.
Keep clear routes to roof doors, tanks and plant, and room for maintenance. On larger commercial roofs, discuss fire-fighting access and DC isolation with the designer and, where needed, Civil Defence.
The design must suit the existing main panel, earthing and meter arrangement. Where the building's distribution board is old or undersized, upgrades may be needed first. Our MEP design team can review this.
Solar PV is different from solar water heating. Dubai Municipality has long required solar hot-water design calculations for certain new buildings as part of the building permit, under its green building rules. Rooftop PV competes for the same roof space, so on new villas it makes sense to plan both together with the Al Sa'fat compliance work.
We don't publish DEWA charges or equipment prices, because they depend on system size and design and are set by DEWA and suppliers. Our quotation separates authority charges, the enrolled contractor's supply and installation price, and our coordination fee. The main variables are:
If the solar work is part of a bigger renovation, we fold it into the wider NOC coordination for the project so the developer sees one coherent package.
Yes, for any system connected to DEWA's grid. The application is made by a DEWA-enrolled Shams Dubai consultant or contractor, who obtains the solar NOC and design approval before installation and arranges DEWA's inspection and connection afterwards.
A tenant can apply, but DEWA requires the owner's NOC, and the tenancy contract forms part of the documents. In a master community the developer's consent may also be needed.
Under net metering, surplus electricity is exported to DEWA's network and credited against future consumption. DEWA states that the credit rolls over to later bills, but it cannot be transferred to a new owner or tenant.
DEWA's guidance allows generators on rooftops, façades and other existing structures. A shade structure such as a car-park canopy may be an option, but it can need its own developer and building approvals.
In most master communities, yes. Rooftop equipment changes the external appearance, which developers control through their modification guidelines. We check the specific community's rules before design starts.
On this page
Thinking about solar?
Send a roof photo, your community name and whether you own or rent. We will tell you which consents you need before you talk to installers.
Guide
DEWA connection fees, review times, system size limits and how net metering credits work.
Read more
Guide
The useful starting point for an electrical application is an accurate description of connected equipment and the existing supply.
Read more
Guide
A U-value describes thermal transmittance through a building element.
Read more
Service
Match electrical and water requirements to your project’s real demand. We help organise the project information and coordinate with the appropriately qualified parties responsible for DEWA-related design and applications.
Read more
Service
Understand how proposed changes or observed concerns affect a building’s structural assessment. We help define the investigation brief and coordinate the records required by the responsible structural professional.
Read more
Service
Coordinate mechanical, electrical and plumbing systems around the proposed space and equipment. We help connect the architectural layout to practical service routes, demand information and technical submissions.
Read more
Service
Integrate sustainability requirements into the design and documentation of a building project. We help organise the evidence and coordination needed for the applicable Al Sa’fat requirements.
Read more
Service
One team to track every NOC your Dubai project needs: developer, building management, DEWA, Civil Defence, RTA, telecoms and more, sequenced around your permit.
Read more
Share a few details and we will tell you which approvals apply, what documents you need and how we can help. There is no obligation.