Before a building or unit gets power and water, DEWA has to clear the project, approve the load and design, inspect the installation and fit the meters. Here is how each DEWA NOC and approval fits together, who files it and what to prepare.
A DEWA NOC is the no objection certificate in which Dubai Electricity and Water Authority confirms it has no objection to a building permit from an electricity or water supply point of view. A DEWA-enrolled consultant or contractor applies for it online, through Dubai Municipality's building permit system for municipality projects or through DEWA's own channels elsewhere, and DEWA does not charge for the NOC itself. The building NOC is only the first stage. The DEWA approval process then continues with load and design approval, payment of the connection invoice, inspection and, finally, meters and supply.
This guide is written by the DXB Approval Team. We prepare load schedules and electrical drawings, coordinate DEWA applications through enrolled consultants and contractors, and follow files through to connection for owners, developers and fit-out tenants. DEWA makes every decision, so treat the timelines here as planning ranges and follow the conditions on your own approvals.
People use "DEWA NOC" for several different things. Strictly, the DEWA building NOC is a clearance issued for electricity and, separately, for water, telling the permit authority that DEWA can serve the plot. It does not approve your electrical design or connect anything.
DEWA now bundles the electricity building NOC and the connection request into one application, called Getting Electricity Permits & Connections. Once DEWA verifies that application, it issues the approved electricity NOC, the LV (low-voltage) design approval and an estimated invoice together.
Other DEWA NOCs, such as the infrastructure NOC for digging near DEWA cables and pipes, have nothing to do with a building permit. The table below sorts them out.
| DEWA approval | When it applies | Who files it |
|---|---|---|
| Building NOC, electricity | New buildings and works needing a building permit | Enrolled consultant or contractor |
| Building NOC, water | The same, for the water supply | Enrolled consultant or contractor |
| Getting Electricity Permits & Connections | Electricity NOC, LV design approval and connection in one application; also used for additional load or temporary supply | Enrolled consultant or contractor |
| Getting Electricity Fit-out Connections | Supply to a shop, office or other unit fitted out inside a building DEWA already serves | Enrolled consultant or contractor |
| Getting Water Connections | Temporary, permanent or upgraded water supply | Enrolled consultant or contractor |
| Infrastructure NOC | Works in the right of way or near DEWA reservations, cables or pipes | Registered consultant, contractor or developer, often via RTA's e-NOC system |
| Demolishing permit, electricity and water | Before a building is demolished | Enrolled consultant or contractor |
| Solar permits and connections (Shams Dubai) | Rooftop solar connected to the grid | DEWA-enrolled solar consultant or contractor |
For properties under Dubai Municipality, an owner wanting to increase the electrical current or add a meter may also need a municipality NOC addressed to DEWA, requested through the Build in Dubai platform.
Plan for DEWA whenever a project creates a new supply point or changes how much power or water a property uses:
Cosmetic works that leave the installation and load unchanged usually need no DEWA application, but confirm with your landlord or developer.
DEWA's builder services are filed online by enrolled consultants and contractors only. An owner cannot submit a building NOC personally or on paper, which is why owners usually appoint a consultant or contractor and link the project to their own DEWA profile.
| Party | Role in the DEWA application |
|---|---|
| Owner or tenant | Documents and equipment brief, pays DEWA invoices, signs the supply terms |
| MEP consultant | Load calculation, schedules, single line diagram and layouts |
| Enrolled consultant or contractor | Files the applications and answers DEWA's comments |
| Electrical contractor | Installs and tests the work, requests inspection |
| Landlord or building management | Confirms the unit's allocated load, issues the landlord NOC |
| DEWA | Reviews, invoices, inspects, fits meters and releases supply |
The exact list depends on the service and the load, but expect the following for a new electricity connection:
The water NOC adds a setting-out plan showing the water tank. A fit-out connection uses the base building's approved load schedules, the unit's board schedule and layouts, and a landlord NOC in DEWA's format. What each drawing must contain is covered in our guide to MEP drawings for DEWA and Civil Defence.
For a new building, the route usually runs like this:
For new buildings the permanent connection is closely tied to completion. Our guide to the building completion certificate explains how that final stage links to DEWA.
The times below are DEWA's own service times, counted from a complete application. They do not include design time, comments, resubmissions or site works, so plan for some slack around each stage.
| DEWA stage | DEWA service time |
|---|---|
| Building NOC, electricity | 2 working days |
| Building NOC, water | 3 working days |
| LV design approval, loads up to 150 kW | 1 working day |
| LV design approval, 151 to 400 kW | 2 working days |
| LV design approval, above 400 kW | 3 working days |
| Connection cost (invoice) issued | 3 working days |
| LV inspection | 1 working day from the request |
| Fit-out design approval | 1 working day |
| Water meter, small connection | 3 working days after payment, once the site is ready |
| Water meter, large connection | 5 working days after payment, subject to the scheduled shutdown |
On fees, there is no DEWA charge for the building NOC application, the fit-out connection application or registering a water connection. The connection charges themselves are invoiced by DEWA and depend on the load, the type of connection, materials and site conditions, so we do not quote them as fixed figures. The connection cost estimate stays valid for one year from issue, and a security deposit is paid before supply is released.
In a multi-tenant building, each unit has a share of the building's approved supply. A fit-out works within that share: DEWA approves the unit's boards and layouts, inspects the installed work, issues one invoice covering the estimate and security deposit, then fits the meter. Where a premises with an installed meter gets an Ejari, DEWA's linked system can prompt the owner or tenant to request the connection.
If the new use needs more than the unit's share, such as a restaurant kitchen or server room, the landlord must agree and the building may need an additional load application. Check the allocation before signing a lease or ordering equipment. The authority fit-out permit and Civil Defence approval run alongside; our page on fit-out permits in Dubai shows how the layers fit.
Water follows a similar path: the water building NOC, then a temporary, permanent or upgrade connection application with approved shop drawings and a premises details sheet. DEWA visits the site, issues a cost estimate, and connects the meter once it is paid and the site and other NOC clearances are ready. Settle the tank position and plumbing design early.
Rooftop solar has its own DEWA route under Shams Dubai, filed by a DEWA-enrolled solar consultant or contractor, with design approval, inspection, performance testing for larger systems and a generation meter. Our Shams Dubai solar guide covers it in detail.
A home or workplace charger adds load to the same board and account, so the revised load may need DEWA approval first. See our guide to EV charger approvals.
A DEWA building NOC for electricity stays valid for two years in normal growth areas, or one year in major project areas, for the follow-on connection application. If a project stalls, check validity before restarting. If DEWA returns an application, it must be resubmitted within 30 days or the system cancels it automatically. An infrastructure NOC is valid for six months and should be renewed shortly before it expires.
Most DEWA delays start in the drawings, not the forms:
Where several authorities are involved, our NOC coordination service keeps the developer, DEWA, Civil Defence and RTA steps in order, and our MEP design and approvals team prepares the load calculations DEWA reviews.
Appoint a DEWA-enrolled consultant or contractor. They submit the building NOC online, through Dubai Municipality's building permit system for municipality projects or through DEWA's building NOC service for projects licensed elsewhere, and link the project to you as owner.
The building NOC is quick, DEWA's service time is 2 working days for electricity once the application is complete. The full process to energisation depends on design comments, payment, site progress and inspections, so it runs alongside the build.
There is no DEWA charge for the building NOC. Connection charges and the security deposit are separate, invoiced by DEWA according to the load and connection type.
Usually, yes, where the unit gets its own supply or the electrical installation changes. DEWA approves the unit's boards and layouts, needs a landlord NOC in its format, and inspects the work before releasing supply.
Not for builder services such as the building NOC and connections, which only enrolled consultants and contractors can file. The owner supplies documents, pays invoices and signs DEWA's supply terms.
Send us your drawings or equipment list and a short description of the project. We will confirm which DEWA approvals apply, prepare the load schedules and drawings, and follow the NOC, design approval and inspections through to connection. See our DEWA approval services or contact the DXB Approval Team for a quote.
On this page
RELATED SERVICE
Match electrical and water requirements to your project’s real demand. We help organise the project information and coordinate with the appropriately qualified parties responsible for DEWA-related design and applications.
Permit and NOC guides
DEWA connection fees, review times, system size limits and how net metering credits work.
View details
Authority guides
How design NOCs and construction NOCs differ.
View details
Fees, timelines and documents
Coordinating the drawing package before submission.
View details
LET’S TALK ABOUT YOUR PROJECT
Tell us the location, property type and work you have in mind.