DEWA NOC and approval process in Dubai, step by step

Before a building or unit gets power and water, DEWA has to clear the project, approve the load and design, inspect the installation and fit the meters. Here is how each DEWA NOC and approval fits together, who files it and what to prepare.

A DEWA NOC is the no objection certificate in which Dubai Electricity and Water Authority confirms it has no objection to a building permit from an electricity or water supply point of view. A DEWA-enrolled consultant or contractor applies for it online, through Dubai Municipality's building permit system for municipality projects or through DEWA's own channels elsewhere, and DEWA does not charge for the NOC itself. The building NOC is only the first stage. The DEWA approval process then continues with load and design approval, payment of the connection invoice, inspection and, finally, meters and supply.

This guide is written by the DXB Approval Team. We prepare load schedules and electrical drawings, coordinate DEWA applications through enrolled consultants and contractors, and follow files through to connection for owners, developers and fit-out tenants. DEWA makes every decision, so treat the timelines here as planning ranges and follow the conditions on your own approvals.

Printed floor plan drawings on a desk with a drafting pencil, scale ruler, tape and a drawing tube

What a DEWA NOC is, and what it is not

People use "DEWA NOC" for several different things. Strictly, the DEWA building NOC is a clearance issued for electricity and, separately, for water, telling the permit authority that DEWA can serve the plot. It does not approve your electrical design or connect anything.

DEWA now bundles the electricity building NOC and the connection request into one application, called Getting Electricity Permits & Connections. Once DEWA verifies that application, it issues the approved electricity NOC, the LV (low-voltage) design approval and an estimated invoice together.

Other DEWA NOCs, such as the infrastructure NOC for digging near DEWA cables and pipes, have nothing to do with a building permit. The table below sorts them out.

DEWA approvals and NOCs a project may need

DEWA approvalWhen it appliesWho files it
Building NOC, electricityNew buildings and works needing a building permitEnrolled consultant or contractor
Building NOC, waterThe same, for the water supplyEnrolled consultant or contractor
Getting Electricity Permits & ConnectionsElectricity NOC, LV design approval and connection in one application; also used for additional load or temporary supplyEnrolled consultant or contractor
Getting Electricity Fit-out ConnectionsSupply to a shop, office or other unit fitted out inside a building DEWA already servesEnrolled consultant or contractor
Getting Water ConnectionsTemporary, permanent or upgraded water supplyEnrolled consultant or contractor
Infrastructure NOCWorks in the right of way or near DEWA reservations, cables or pipesRegistered consultant, contractor or developer, often via RTA's e-NOC system
Demolishing permit, electricity and waterBefore a building is demolishedEnrolled consultant or contractor
Solar permits and connections (Shams Dubai)Rooftop solar connected to the gridDEWA-enrolled solar consultant or contractor

For properties under Dubai Municipality, an owner wanting to increase the electrical current or add a meter may also need a municipality NOC addressed to DEWA, requested through the Build in Dubai platform.

When DEWA approval is needed

Plan for DEWA whenever a project creates a new supply point or changes how much power or water a property uses:

  • new villas and buildings
  • extensions and added load, such as a pool plant room or heavy air conditioning
  • commercial fit-outs that need their own supply
  • warehouses with machinery, cold rooms or large cooling loads
  • rooftop solar and EV chargers
  • excavation near DEWA cables or pipes, and demolition

Cosmetic works that leave the installation and load unchanged usually need no DEWA application, but confirm with your landlord or developer.

Who applies for a DEWA NOC

DEWA's builder services are filed online by enrolled consultants and contractors only. An owner cannot submit a building NOC personally or on paper, which is why owners usually appoint a consultant or contractor and link the project to their own DEWA profile.

PartyRole in the DEWA application
Owner or tenantDocuments and equipment brief, pays DEWA invoices, signs the supply terms
MEP consultantLoad calculation, schedules, single line diagram and layouts
Enrolled consultant or contractorFiles the applications and answers DEWA's comments
Electrical contractorInstalls and tests the work, requests inspection
Landlord or building managementConfirms the unit's allocated load, issues the landlord NOC
DEWAReviews, invoices, inspects, fits meters and releases supply

DEWA documents and drawings checklist

The exact list depends on the service and the load, but expect the following for a new electricity connection:

  • affection plan, only for projects in Dubai free zone areas
  • setting-out plan, with the meter location on smaller loads
  • a project information letter for proposed loads of 400 kW or more
  • total connected load and maximum demand, with MDB and SMDB schedules
  • load schedules for the final distribution boards
  • single line diagram with LV distribution and tariff metering
  • ground floor plan showing the substation, LV room, meters and main boards
  • lighting and power wiring layouts and a premises details sheet
  • DEWA's supply terms, signed by the owner before supply is released

The water NOC adds a setting-out plan showing the water tank. A fit-out connection uses the base building's approved load schedules, the unit's board schedule and layouts, and a landlord NOC in DEWA's format. What each drawing must contain is covered in our guide to MEP drawings for DEWA and Civil Defence.

The DEWA approval process, step by step

For a new building, the route usually runs like this:

  1. List the equipment. Air conditioning, lighting, pumps, lifts and machinery drive everything that follows.
  2. Calculate the load. The MEP engineer applies diversity, since not everything runs at full power at once, to give connected load and maximum demand.
  3. Apply for the building NOC. For Dubai Municipality projects this goes through the municipality's building permit system and reaches DEWA digitally; projects licensed by other authorities apply through DEWA.
  4. Get LV design approval. The schedules and drawings are reviewed, and comments are answered with revised documents.
  5. Pay the invoice. DEWA issues an estimate for the connection charges, which the owner pays.
  6. HV substation inspection, if there is one. Larger loads may need a DEWA substation on the plot, inspected once the room is ready.
  7. LV inspection. When the installation and wiring are complete, the contractor requests inspection with site photos. Snags are fixed and inspection is requested again.
  8. Meters and energisation. DEWA confirms the date, installs the meters and releases the supply.

For new buildings the permanent connection is closely tied to completion. Our guide to the building completion certificate explains how that final stage links to DEWA.

DEWA timelines and fees in 2027

The times below are DEWA's own service times, counted from a complete application. They do not include design time, comments, resubmissions or site works, so plan for some slack around each stage.

DEWA stageDEWA service time
Building NOC, electricity2 working days
Building NOC, water3 working days
LV design approval, loads up to 150 kW1 working day
LV design approval, 151 to 400 kW2 working days
LV design approval, above 400 kW3 working days
Connection cost (invoice) issued3 working days
LV inspection1 working day from the request
Fit-out design approval1 working day
Water meter, small connection3 working days after payment, once the site is ready
Water meter, large connection5 working days after payment, subject to the scheduled shutdown

On fees, there is no DEWA charge for the building NOC application, the fit-out connection application or registering a water connection. The connection charges themselves are invoiced by DEWA and depend on the load, the type of connection, materials and site conditions, so we do not quote them as fixed figures. The connection cost estimate stays valid for one year from issue, and a security deposit is paid before supply is released.

Fit-outs and load changes in existing buildings

In a multi-tenant building, each unit has a share of the building's approved supply. A fit-out works within that share: DEWA approves the unit's boards and layouts, inspects the installed work, issues one invoice covering the estimate and security deposit, then fits the meter. Where a premises with an installed meter gets an Ejari, DEWA's linked system can prompt the owner or tenant to request the connection.

If the new use needs more than the unit's share, such as a restaurant kitchen or server room, the landlord must agree and the building may need an additional load application. Check the allocation before signing a lease or ordering equipment. The authority fit-out permit and Civil Defence approval run alongside; our page on fit-out permits in Dubai shows how the layers fit.

Water connections

Water follows a similar path: the water building NOC, then a temporary, permanent or upgrade connection application with approved shop drawings and a premises details sheet. DEWA visits the site, issues a cost estimate, and connects the meter once it is paid and the site and other NOC clearances are ready. Settle the tank position and plumbing design early.

Rooftop solar and EV chargers

Rooftop solar has its own DEWA route under Shams Dubai, filed by a DEWA-enrolled solar consultant or contractor, with design approval, inspection, performance testing for larger systems and a generation meter. Our Shams Dubai solar guide covers it in detail.

A home or workplace charger adds load to the same board and account, so the revised load may need DEWA approval first. See our guide to EV charger approvals.

Validity, returns and common delays

A DEWA building NOC for electricity stays valid for two years in normal growth areas, or one year in major project areas, for the follow-on connection application. If a project stalls, check validity before restarting. If DEWA returns an application, it must be resubmitted within 30 days or the system cancels it automatically. An infrastructure NOC is valid for six months and should be renewed shortly before it expires.

Most DEWA delays start in the drawings, not the forms:

  • equipment lists changing after the load calculation
  • board schedules that do not add up to the declared demand or contradict the single line diagram
  • a unit's new load exceeding the landlord's allocation
  • substation space discovered late on larger projects
  • a missing landlord NOC on a fit-out
  • inspection requested before the wiring and labelling are complete

Where several authorities are involved, our NOC coordination service keeps the developer, DEWA, Civil Defence and RTA steps in order, and our MEP design and approvals team prepares the load calculations DEWA reviews.

Frequently asked questions

Appoint a DEWA-enrolled consultant or contractor. They submit the building NOC online, through Dubai Municipality's building permit system for municipality projects or through DEWA's building NOC service for projects licensed elsewhere, and link the project to you as owner.

The building NOC is quick, DEWA's service time is 2 working days for electricity once the application is complete. The full process to energisation depends on design comments, payment, site progress and inspections, so it runs alongside the build.

There is no DEWA charge for the building NOC. Connection charges and the security deposit are separate, invoiced by DEWA according to the load and connection type.

Usually, yes, where the unit gets its own supply or the electrical installation changes. DEWA approves the unit's boards and layouts, needs a landlord NOC in its format, and inspects the work before releasing supply.

Not for builder services such as the building NOC and connections, which only enrolled consultants and contractors can file. The owner supplies documents, pays invoices and signs DEWA's supply terms.

Get help with your DEWA NOC

Send us your drawings or equipment list and a short description of the project. We will confirm which DEWA approvals apply, prepare the load schedules and drawings, and follow the NOC, design approval and inspections through to connection. See our DEWA approval services or contact the DXB Approval Team for a quote.

RELATED SERVICE

DEWA approval coordination

Match electrical and water requirements to your project’s real demand. We help organise the project information and coordinate with the appropriately qualified parties responsible for DEWA-related design and applications.

LET’S TALK ABOUT YOUR PROJECT

A clear next step starts
with the right brief.

Tell us the location, property type and work you have in mind.

This form sends your enquiry to Dubai Authority Approvals by email. It does not submit an application to an authority. Please avoid identity documents in the initial enquiry; drawings can be shared once we reply.