Setting up a restaurant in Dubai: approvals needed

Opening a restaurant in Dubai involves a chain of approvals. Here they are in the order they usually come, so you can plan from lease to opening day.

Opening a restaurant in Dubai means coordinating a business licence, a suitable premises, the landlord's consent, a fit-out permit, Civil Defence approval, food safety approvals and, depending on the concept, additional permits for signage, outdoor seating or specific activities. Each depends on the one before. Getting the order wrong, or missing a step, is the most common reason restaurants open later than planned.

This guide sets out the approvals needed to open a restaurant, in the order they usually come, and the decisions that keep the process on track. For kitchen layout rules, see our guide to restaurant kitchen layout requirements, and for project support, our restaurant and café fit-out approval service.

The approvals at a glance

StageApprovalIssued by
1Business activity and licence (initial)The licensing authority for the location (mainland or free zone)
2Premises suitability and leaseLandlord, with checks on permitted use
3Landlord fit-out NOCLandlord or mall management
4Fit-out permitThe authority for the area
5Civil Defence approvalDubai Civil Defence
6Food safety approvalsThe food safety authority for the location
7Utility approvalsDEWA, gas and others where needed
8Additional permitsSignage, outdoor seating, special activities
9Fit-out completion and inspectionsAuthority, Civil Defence, food safety
10Final licence and openingLicensing authority

Stage by stage

1. Define the concept and business activity

The concept, whether café, fine dining, quick service, cloud kitchen or bakery, decides the licence activity, the kitchen and the premises you need. Settle the menu and service style before looking for premises.

2. Choose suitable premises

Check that the unit's permitted use allows food service, that the landlord allows your type of cooking, and that there is a route for kitchen exhaust, drainage for grease traps, adequate power and, if needed, gas. Signing a lease before these checks is the riskiest step in the process.

3. Obtain the landlord's fit-out NOC

The landlord or mall reviews the design against its fit-out guidelines, including shopfront, signage, exhaust and services, and issues its NOC.

4. Apply for the fit-out permit

The fit-out drawings, with the landlord NOC, are submitted to the authority for the area, such as Dubai Municipality, DDA or a free zone authority.

5. Civil Defence approval

Fire and life safety, including kitchen hood suppression, gas systems, escape routes and detection, is reviewed and later inspected.

6. Food safety approvals

The kitchen layout, finishes, storage and hygiene arrangements are reviewed by the food safety authority, followed by inspection before opening.

7. Utilities

DEWA approvals for load changes and gas approvals where gas is used.

8. Additional permits

Signage, outdoor seating and certain activities may need separate permits. See our signage and tent permit service and, if you plan to serve shisha, our shisha café approval service.

9. Completion and inspections

After the works, inspections by the authority, Civil Defence and food safety lead to the fit-out completion and the food establishment approval.

10. Final licence and opening

With the approvals in place, the trade licence is finalised and the restaurant can open.

How long it takes in 2027

For a 2027 opening, times depend on the location, the concept and how quickly decisions are made. As a guide, authority review times for complete applications are typically an estimated 3 to 7 working days for Dubai Municipality and 7 to 15 working days for DDA, with Civil Defence typically 15 to 20 working days. Design, landlord review, fit-out works and food safety inspections add to the overall programme, which for a full restaurant fit-out usually runs to several months.

Decisions that keep the process on track

  • Finalise the menu and kitchen equipment before the layout
  • Agree the exhaust route with the landlord before designing the kitchen
  • Check power and gas availability before signing the lease
  • Coordinate the fire, MEP and kitchen designs from the start
  • Keep a permission register with owners and dates for every approval

Mall, street-front and hotel restaurants

Mall units come with detailed fit-out guidelines covering shopfronts, signage, exhaust routes, grease traps, working hours and the mall's own fire systems. The mall's review is often as demanding as the authority's.

Street-front units give more control over the shopfront and outdoor seating, but may need the tenant to arrange more services, such as exhaust routes and grease management, and to consider neighbours.

Hotel restaurants work within the hotel's operations, fire strategy and kitchen infrastructure, with the hotel's management as the key stakeholder alongside the authorities.

Common mistakes

  • Signing a lease before confirming the unit suits food service
  • Designing the kitchen before agreeing the exhaust route
  • Ordering equipment before the layout is approved
  • Forgetting signage and outdoor seating permits
  • Treating food safety approval as a final formality
  • Not planning time for inspections before opening

Frequently asked questions

Usually defining the business activity and starting the licence, alongside checking that the premises suit food service.

Most food outlets with cooking or significant fit-out involve Civil Defence review.

The food safety authority reviews hygiene and layout; Civil Defence reviews fire safety.

Generally no. Opening usually depends on completion and food safety approval.

Malls have their own fit-out guidelines, including shopfronts, signage and exhaust routes.

Get help opening your restaurant

Send us your concept, menu and the units you are considering. We will check premises suitability, build your permission register and coordinate the landlord, fit-out, Civil Defence and food safety approvals.

RELATED SERVICE

Restaurant and F&B approval

Coordinate the food operation, kitchen design and premises approvals before committing to a fit-out. We help bring the operator’s menu and equipment brief into the technical submission process.

LET’S TALK ABOUT YOUR PROJECT

A clear next step starts
with the right brief.

Tell us the location, property type and work you have in mind.

This form sends your enquiry to Dubai Authority Approvals by email. It does not submit an application to an authority. Please avoid identity documents in the initial enquiry; drawings can be shared once we reply.