Rejections and common mistakes

Why Trakhees approvals get rejected or delayed

Before changing your drawings, find out why the Trakhees application came back. Here are the common causes and how to fix each one.

When a Trakhees application comes back with comments or is rejected, the instinct is to start changing drawings. A better first step is to understand the actual reason. Many Trakhees delays have nothing to do with the design itself: the wrong service was selected, a prerequisite NOC was missing, documents didn't match, or environment, health and safety requirements weren't addressed. Classifying the issue correctly saves time and avoids new errors.

This guide explains the most common reasons Trakhees applications are rejected or delayed, how to investigate a comment, and how to fix each issue. For the permit process, see our guide to the Trakhees permit process, and for project support, our Trakhees approval service.

Start by investigating the comment

Before changing anything:

  1. Read the comment exactly as written, and identify which department issued it, such as the Civil Engineering Department (CED) or Environment, Health and Safety (EHS).
  2. Identify the type of issue: procedural, documentary, technical design or EHS.
  3. Check the related parts of the submission, not just the item mentioned.
  4. Clarify through official channels if the comment is unclear.

Why the source of the comment matters

The same apparent problem can have different causes depending on which department raised it. A fire safety comment from CED may point to a drawing inconsistency, while one from EHS may point to the materials being stored. Fixing the right thing first time depends on knowing who asked and why.

The common causes

1. Wrong service selected

Trakhees has separate services for new buildings, modifications, completions, modification completions and specific works such as racking revisions. Applying under the wrong one leads to return.

Fix: confirm the correct service for the scope before submitting.

2. Missing or expired prerequisite NOCs

In Nakheel communities, the Nakheel NOC is usually required; in JAFZA, the JAFZA modification NOC. A missing or expired NOC stops the application.

Fix: obtain and attach current NOCs, and track their validity. A lapsed modification permit may only be revalidated with a valid master developer NOC, so keep both current. See the Nakheel application process and JAFZA warehouse modifications.

3. Inconsistent drawings

Architectural, structural, MEP and fire drawings that disagree, or drawings that don't match the site plan.

Fix: coordinate all disciplines and cross-check before resubmission.

4. Missing calculations or specifications

Structural calculations, load schedules or material specifications not provided.

Fix: include the technical information the service requires.

5. EHS requirements not addressed

For industrial projects, missing information about stored materials, safety data sheets, ventilation or fire safety.

Fix: describe the operation and materials clearly and address EHS requirements in the design.

6. Contractor or consultant registration issues

The named contractor or consultant isn't registered with Trakhees, or the registration has expired.

Fix: use registered firms and check their status before naming them. See Dubai Municipality licence categories for how classification works.

7. Site doesn't match the records

For modifications, the existing building differs from the approved drawings because of earlier unapproved works.

Fix: survey the building, prepare as-built drawings and resolve earlier works through the appropriate route.

8. Works started before approval

Inspectors find works already under way.

Fix: stop work, seek advice and regularise through the correct process.

Classifying the issue

TypeExamplesTypical fix
ProceduralWrong service, sequencingReapply under the correct service
DocumentaryMissing or expired NOCs, inconsistent documentsUpdate and resubmit documents
Technical designDrawing conflicts, missing calculationsRevise and coordinate drawings
EHSHazardous materials, ventilation, fireAddress EHS requirements in the design
RegistrationUnregistered contractor or consultantAppoint registered firms
SiteUnapproved works, works before permitSurvey and regularise

Preventing comments before you submit

CheckDone
Correct Trakhees service selected for the scope☐
Current developer or JAFZA NOC attached and matching the scope☐
Architectural, structural, MEP and fire drawings coordinated☐
Calculations and specifications included☐
Operation and stored materials described, with safety data sheets where needed☐
Consultant and contractor registered with Trakhees☐
Existing building matches the approved records☐
No works started before approval☐

Running through this list before submission removes most of the reasons applications come back.

How long delays add

Trakhees approval typically takes an estimated 8 to 20 days once a complete application is submitted. Each round of comments restarts part of that review, so a submission that needs two or three rounds can take several times longer than one that is complete first time. Developer NOC renewals and regularisation of earlier works add further time.

Frequently asked questions

Common reasons include the wrong service, missing NOCs, inconsistent drawings, missing calculations, EHS gaps or registration issues.

CED comments concern engineering and building aspects; EHS comments concern environment, health and safety.

In Nakheel communities and JAFZA, the relevant NOC is usually a prerequisite.

Yes, once every comment is addressed and the whole set is checked.

Stop and seek advice. Unpermitted works need to be regularised through the correct process.

Yes, through its official channels. A short clarification can prevent a resubmission that misses the point of the comment.

They are most common for industrial and warehouse projects, but EHS aspects such as fire safety and site safety can apply to other projects too.

Rarely. Most rejections can be resolved by correcting the procedure, documents or design and resubmitting.

Get help with a returned Trakhees application

Send us the comments and your submission. We will identify the real issue, fix it at its source and prepare a complete resubmission.

RELATED SERVICE

Trakhees approval

Prepare modification or construction submissions for a property under Trakhees jurisdiction. We help connect the proposed work to the appropriate PCFC service and organise the information needed for review.

LET’S TALK ABOUT YOUR PROJECT

A clear next step starts
with the right brief.

Tell us the location, property type and work you have in mind.

This form sends your enquiry to Dubai Authority Approvals by email. It does not submit an application to an authority. Please avoid identity documents in the initial enquiry; drawings can be shared once we reply.