Authority approvals · Electricity & water
For owners, developers and fit-out tenants who need DEWA's building NOC, load approval or a new connection. We prepare the load schedules and drawings, coordinate the enrolled consultant and contractor, and follow the file through to energisation.
A building can have every permit in place and still sit dark. In Dubai, power and water arrive only after the Dubai Electricity and Water Authority (DEWA) has accepted the load, checked the installation and released the supply, and that sequence starts long before the contractor finishes.
DEWA's involvement in a project comes in layers. There is an early no-objection certificate that lets the building permit go ahead. There is a load and design approval that fixes how much power the building may draw and how it is distributed. And there are inspections at the end before meters are fitted and the supply is switched on. Each layer depends on drawings and schedules that have to agree with each other.
We are a private consultancy, not part of DEWA. DEWA alone approves loads and connects supply. Many DEWA services can only be filed by consultants and contractors enrolled with DEWA, so we coordinate submissions through an enrolled consultant or contractor where that is required, and handle the technical preparation and follow-up around it.
Almost any project that creates a new supply point or changes the electrical or water demand of a property ends up with DEWA. The common triggers are:
A new villa, residential block, warehouse or commercial building needs a DEWA building NOC for electricity and water as part of its building permit, then a permanent connection once the installation is complete.
Adding floors, a large extension, a pool plant room or heavy air-conditioning can push demand beyond what the existing connection was approved for. The revised load has to be designed and approved before it is connected.
A tenant fitting out a shop, office, clinic or restaurant inside an existing building needs its own distribution design approved and inspected before the unit's supply is released.
DEWA lists a separate electricity and water service for demolition permits, and works near its cables, substations or pipelines need its no-objection before excavation.
Rooftop solar also runs through DEWA, under the Shams Dubai initiative, but it has its own enrolment and connection route. We cover it on our solar panel approval page.
DEWA's builder services are separate applications, though some are now bundled. Knowing which one applies avoids filing the wrong request.
| DEWA service | What it does | Who files it |
|---|---|---|
| Building No Objection Certificate (electricity / water) | Confirms DEWA has no objection to the building permit from a supply point of view | Enrolled consultant or contractor |
| Getting Electricity Permits & Connections | Bundles the electricity building NOC with the connection request in a single application, followed by payment, inspections and energisation | Enrolled consultant or contractor |
| Getting Water Connections | The equivalent route for the building's water supply | Enrolled consultant or contractor |
| Getting Electricity Fit-out Connections | Design approval, LV inspection and supply for a unit fitted out inside a building that DEWA already serves | Enrolled contractor |
| Demolishing permits (electricity / water) | DEWA's clearance before a building is demolished | Enrolled consultant or contractor |
For projects permitted by Dubai Municipality, DEWA says owners don't need to apply through DEWA's own channels for the building NOC. The request is submitted inside the municipality's building permit system and passed to DEWA digitally. Projects licensed by other authorities, such as free zones and special development areas, apply directly through DEWA. Read more about the municipality side on our Dubai Municipality approval page.
DEWA's lists are short compared with a building permit, but every item is technical and must match the rest of the file. Depending on the service, expect to prepare:
These schedules come out of the electrical design. If you don't yet have an MEP consultant, our MEP design and approvals service prepares the load calculations and drawings DEWA reviews.
For a new building, the DEWA route runs alongside the building permit and finishes near completion. A typical path:
The MEP consultant calculates connected load and maximum demand from the architectural layout, the air-conditioning design and the building use. This number decides whether the plot needs a DEWA substation.
MEP consultant
The electricity and water building NOCs are requested, through the building permit system for Dubai Municipality projects or directly with DEWA elsewhere. DEWA lists both as free of charge.
Enrolled consultant · DEWA
The connection request, with load schedules and drawings, is filed and reviewed. Comments on load figures or board schedules are answered with revised documents.
Enrolled consultant or contractor · DEWA
DEWA issues an invoice for the applicable connection charges, which the owner pays before the connection proceeds.
Owner
If the project includes a DEWA substation, DEWA inspects it once the substation room is ready.
Contractor · DEWA inspectors
When the electrical installation and wiring are complete on site, the contractor requests the low-voltage inspection and submits site photos and supporting documents.
Electrical contractor · DEWA
With inspections passed and the owner's supply terms signed, DEWA fits the meters and releases the supply. The account is then activated in the occupier's name.
DEWA · owner
Fit-outs follow a shorter version: design approval of the unit's boards and layouts, LV inspection of the installed work, invoice, then supply. Our fit-out approval page shows how this sits beside the authority fit-out permit and Civil Defence.
The load figure is the single most important number in a DEWA file. It drives the size of the incoming supply, the meter arrangement and whether DEWA needs space on the plot for its own equipment.
DEWA's regulations for electrical installations require space for a DEWA substation within the building or plot where the total connected load exceeds 400 kW, and DEWA can ask for one at lower loads in some circumstances. On a mid-size building or a warehouse with heavy cooling, that requirement shapes the ground-floor layout, so it should be settled during concept design rather than after the architecture is fixed.
For existing buildings, added load is where projects slip. An owner adds a pool, a cold room or a large kitchen, and the extra demand is never put to DEWA. The supply may cope for a while, but the installation no longer matches what was approved, and that can surface at a later inspection, at a tenancy change or when the property is sold.
DEWA lists the building NOC itself as free, and its building NOC page states that, for projects in the building permit system, the NOC is processed within three working days from submission. DEWA also lists short service times for fit-out design approval and LV inspection. These standards apply once a complete application is in, and they don't include the time to design, answer comments or finish the installation.
Connection charges are a different matter. They are invoiced by DEWA according to the load and the type of connection, so we don't quote them as fixed figures. Your quotation from us separates DEWA's charges, paid directly to DEWA, from our consultancy fee.
Validity matters too. DEWA's service guide gives the electricity building NOC two years in normal growth areas and one year in major project areas for the follow-on connection application. A project that stalls can find its NOC lapsed when it restarts. For a fuller timeline across all authorities, see how long a building permit takes in Dubai.
Most clients come to us either at design stage, when they want the DEWA side planned properly, or near handover, when a connection has stalled. In both cases we:
For a step-by-step guide aimed at owners, read the DEWA approval process step by step.
DEWA's building NOC and connection services are designed for enrolled consultants and contractors. For Dubai Municipality projects the NOC request goes through the municipality's building permit system. The owner provides ownership documents and signs DEWA's supply terms before the supply is released.
DEWA lists the building NOC for electricity and water as free of charge. Connection charges and other invoices are separate and depend on the load and the type of connection.
Usually, yes. A fit-out connection needs the unit's distribution board schedules and lighting and power layouts approved, a landlord NOC in DEWA's format, and an LV inspection of the installed work before supply is released to the unit.
DEWA's electrical regulations call for substation space within the plot or building where the total connected load exceeds 400 kW, and DEWA may ask for one at lower loads in some cases. Your MEP consultant should confirm this at concept stage.
No. We are a private consultancy. DEWA alone approves loads, inspects installations and connects supply. We prepare and coordinate the applications.
On this page
Connection stuck or load unclear?
Send us the plot or unit details and your latest load schedule. We will tell you what DEWA will need next.
Guide
The useful starting point for an electrical application is an accurate description of connected equipment and the existing supply.
Read more
Guide
A practical fit-out register lists each permission, issuer, scope, owner and status.
Read more
Guide
A useful completion file grows during the work.
Read more
Guide
DEWA’s Shams Dubai guidance explains the grid-connected solar framework, with enrolled specialists involved in applications.
Read more
Service
Coordinate mechanical, electrical and plumbing systems around the proposed space and equipment. We help connect the architectural layout to practical service routes, demand information and technical submissions.
Read more
Service
Get support for Dubai Municipality approval: drawings, NOCs, permits, submissions and completion coordination. Check the approval route for your project.
Read more
Service
One team to track every NOC your Dubai project needs: developer, building management, DEWA, Civil Defence, RTA, telecoms and more, sequenced around your permit.
Read more
Service
Fit-out approval for commercial and residential units in Dubai: landlord NOC, DM, DDA or Trakhees permit, Civil Defence, documents, process and completion.
Read more
Service
Rooftop solar on a Dubai villa, warehouse or building: DEWA Shams Dubai NOC, design approval, developer consent, structural checks and grid connection explained.
Read more
Share a few details and we will tell you which approvals apply, what documents you need and how we can help. There is no obligation.