Fitting out a unit in a DDA business district? Here is how the landlord's requirements and the DDA fit-out permit fit together, step by step.
The Dubai Development Authority (DDA) regulates building and fit-out works in many of Dubai's business districts, including Dubai Internet City, Dubai Media City, Dubai Knowledge Park, Dubai Studio City, Dubai Production City and Dubai Outsource City. Tenants often still call it TECOM, after the group that developed these districts. If you are fitting out an office, studio, shop or other unit there, the DDA fit-out permit is the main regulatory approval.
This guide walks through the DDA fit-out permit from a tenant's point of view: what to do before applying, how the landlord's requirements fit in, the review and works stages, and completion. For a detailed list of documents, see our companion guide on documents required for a DDA fit-out permit, and for project support, our DDA approval service.
TECOM Group developed and manages many of the business district buildings. The Dubai Development Authority is the regulator that reviews and approves building and fit-out works in those districts. In practice, tenants deal with both: the building owner or manager (often TECOM or another landlord) for landlord consent, and DDA for the permit.
Every building has fit-out guidelines covering design standards, approved contractors, working hours, deposits and the landlord's own review. Read them first; designs that ignore them get returned by the landlord before DDA ever sees them.
Confirm the electrical load, AC capacity and any chilled water allocated to the unit, especially if you plan a server room, kitchen or heavy equipment.
The application is usually submitted by the fit-out contractor registered with DDA, supported by a designer or consultant for the drawings.
DDA approval typically takes an estimated 7 to 15 working days once a complete application is submitted. The landlord's review, design development, comment rounds, the works themselves and completion add to the overall programme.
In 2027, authority fees for most DDA approvals are an estimated AED 1,020 – 3,000, depending on the area and scope. The fit-out permit fee is area-based. Landlord fees, deposits and professional fees are separate.
Most landlords give tenants a fixed fit-out period, often with reduced or no rent, before the lease starts in full. The approval process eats into that period, so plan it from the date you get the keys:
If the fit-out period looks too short for this sequence, raise it with the landlord before signing, not after.
Some tenants take over a unit with an existing fit-out from the previous occupier. This can save time and money, but any change to partitions, ceilings or services still needs approval, and the existing fit-out must have been properly completed. Ask the landlord for the previous fit-out completion certificate and approved drawings before relying on them.
Usually the tenant's fit-out contractor, registered with DDA, with the tenant's documents and the landlord's NOC.
Yes. DDA expects the landlord's NOC with the application.
No. Works should start only after the permit is issued and site access is arranged with the landlord.
Yes. Fire and life safety is part of the fit-out, and a Civil Defence completion is usually required before DDA's fit-out completion.
No. DDA covers specific districts. Other free zones have their own authorities.
Send us the building, unit and your plans. We will check the landlord's guidelines, prepare the drawings and coordinate the landlord NOC, DDA permit and completion. For office projects, see our office fit-out approval service, and for the fire stage, how Civil Defence approval works.
RELATED SERVICE
Plan a fit-out within the relevant Dubai Development Authority jurisdiction with a coordinated drawing and document package. We help clarify landlord requirements, the permit scope and the information needed from your appointed contractor.
Fees, timelines and documents
The documents required for a DDA fit-out permit in TECOM business districts: tenancy, contractor, landlord NOC and drawings, and how to keep them consistent.
View details
Permit and NOC guides
Fix occupancy and layout assumptions before the drawings.
View details
Communities and developers
Scope the fit-out against the building's approval instructions.
View details
LET’S TALK ABOUT YOUR PROJECT
Tell us the location, property type and work you have in mind.